Encouraging renewable energy supply, based on a thorough understanding of global best practice supplemented by quantitative analysis
New Technology focuses on four core renewable energy technologies: Solar (PV and thermal), the wind, hydro, biomass, geothermal. We provide analysis, optimization and documentation of possible designs and configurations of system in a given situation, using the newest data and relevant tools; general consultancy including choice of technology, type, plant scale/capacity and installation, location/ orientation, functionality, management systems, etc.

Energy Central operating on renewable energy in the center of City of Telavi

Energy Central showcases the mixed use of the following renewable energy sources:
- Wind for electricity production
- Solar for electricity production
- Solar for thermal energy production
- Environment for thermal energy production
Annual production of thermal energy is estimated at 48,180 kWh and electric power at 12,400 kWh.
Total emission reductions from the project activities are 11.02 tons per year.

Overview:

ProjectDemonstrational Green Recreation Zone in the City of Telavi
Venue: Telavi City, Telavi Municipality
Implementer: Enhancing Capacity for Low Emission Development Strategies (EC-LEDS) Clean Energy
Program,Winrock International
Project idea and execution by: New Technology Center LLC
Project Beneficiary: Telavi City Municipality
Energy Central Components:
- Small scale wind turbine
- Photovoltaic panels
- Power battery
- Solar panels for thermal energy
- Heat pump (combined with solar heating to form a geo-solar system)
- Buffer tank
- Water heating tank

Energy-efficient Rehabilitation of #95 Kindergarten in Tbilisi Municipality

Detailed rehabilitation and modernization of Kindergarten #95 in Tbilisi Municipality with renewable energy sources and energy-efficient technologies. Project envisioned restoration of existing building with integrated micro energy system equipped with solar collectors for water, geothermal pumps, photovoltaic, energy-efficient boiler, water harvesting and grey water recycling systems and renovation of building envelope to reduce GHG emissions and provide a pilot for further measures to be taken by Tbilisi Municipality in accordance to its’ SEAP.

Overview:

Project:Project funded by Tbilisi city Hall’s LEPL Tbilisi Technological Development Fund
Location: Tbilisi
Year of Completion:2016
Implementation Period:5 months
Customer: LEPL Tbilisi Technological Development Fund

Heating Station for Kindergarten in Pshaveli Village of Telavi Municipality

Project involved design, planning, engineering and installation of system of hybrid utilization of solar and biomass sourced energy for the kindergarten in Pshaveli. Specific tasks of the project were:

  • Installation of the so-called Green Heating module, which consists of shredder for biomass, small size biomass chips’ storage, biomass boiler, hot water storage and buffer tank, control and monitoring system and photovoltaics that will supply system with required electricity
  • Adding of extra insulation to the roof of the building
  • Installation of LED lighting and its connection to photovoltaics on the street leading to the kindergarten

Use of biomass and solar energy replaces use of natural gas and generates 71,997 kWh annually. Annual production of electricity by Photovoltaic panels amounts to 849 kWh. Total emission reductions from the project activities are 28.8 tons per year.

Overview:

Project:Project funded by USAID for CoM signatory – Telavi Municipality
System of hybrid utilization of solar and biomass sourced energy and consists of the following:
  • shredder for biomass,
  • small size biomass chips’ storage,
  • biomass boiler,
  • hot water storage tank, control and monitoring system
  • and photovoltaics that will supply system with required electricity

Solar Power Station in Bolnisi

Energy Central showcases the use of the solar power for electricity generation. Replacing electrical power supply from the grid with renewable source generated energy in the total amount of 9196 kWh a year.

Overview:

Project:Utilization of Solar Energy Through Centralized Solar Farm in Bolnisi
Location:Bolnisi, Kvemo Kartli Region
Completion:2016
Implementer:Enhancing Capacity for Low Emission Development Strategies (EC-LEDS) Clean Energy Program, Winrock International
Project idea and execution by: New Technology Center LLC
Power station components:65 PCS of Photovoltaic components of 255W. 24 V, 40X970X1670mm with total capacity of 16.5 kW Inverter 3phase, 15 kW